Monitoring Period |
Date Received |
Entry Point | < CFE 95 % Turbidity MCL | < CFE Max Turbidity MCL | CT's Required Met | Chlorine at Entry Point |
---|---|---|---|---|---|---|
May 01, 2024 | Jun 10, 2024 | WTP-A | Y | Y | Y | Y |
Apr 01, 2024 | May 09, 2024 | WTP-A | Y | Y | Y | Y |
Mar 01, 2024 | Apr 10, 2024 | WTP-A | Y | Y | Y | Y |
Feb 01, 2024 | Feb 29, 2024 | WTP-A | Y | Y | Y | Y |
Jan 01, 2024 | Feb 09, 2024 | WTP-A | Y | Y | Y | Y |
Dec 01, 2023 | Jan 11, 2024 Late |
WTP-A | Y | Y | Y | Y |
Nov 01, 2023 | Dec 08, 2023 | WTP-A | Y | Y | Y | Y |
Oct 01, 2023 | Nov 28, 2023 Late |
WTP-A | Y | Y | Y | Y |
Sep 01, 2023 | Oct 10, 2023 | WTP-A | Y | Y | Y | Y |
Aug 01, 2023 | Sep 08, 2023 | WTP-A | Y | Y | Y | Y |
Jul 01, 2023 | Aug 10, 2023 | WTP-A | Y | Y | Y | Y |
Jun 01, 2023 | Jul 10, 2023 | WTP-A | Y | Y | Y | Y |